Tuesday, June 12, 2007

ICTS-PLC first ladder diagram

After studying the manual for sometime, lastly I managed to come out with this one few days back. As you can see now I add the START STOP and EMERGENCY. To run the program, just turn ON the STARTSTOP while for emergency it is set to OFF by default.

Actually for the past one week, not much can be done for project ICTS due to company production planning suddenly change. Now they want to start the operation by 13 June 2007 which meant last week we have to take care other stuffs like machinerries services and many more. As a result the progress for the project was affected.